Request for MACs
- 18 CuW LD Full
- 28 Ti LD Full
- 63 CuW HD Full
- 5 CuW HD Bottom (NTU Rad. test)
- 5 CuW LD Left (NTU Rad. test)
Current lamination stock
- 22 CuW Full
- 11 Ti Full
- 5 CuW HD Bottom
There was no lamination this week, between the gantry on the granite table being dismantled, testing the new measurement jig with the newly cut plates, and other commitments from Yi-Mu's side
Estimated timeline
- This afternoon/First items next week:
- 5 CuW LD Left (This concludes NTU Rad. test requests)
- Next Week (Jan 27. - Jan 31)
- 30-40 CuW Full
No Ti, as we need confirmation of the final meta design + materials cutting
- NN Week (Feb 3 - Feb 7.)
- 30 -40 CuW Full
May be limited by how many CuW plates pass flatness QC, (Jonas is back this week, so we can follow up on defficiencies)
NTU requests - Full request can be sent out Jan 31st
Other request (minus Ti) can be sent out Feb 7th, assuming metal availability