Update from Markus:
- CuW status:
-
30 additional CuW sheets have been ordered through KIT. This is a bit more expensive (~15%) because it was in lower quantity. We don't expect price changes for build orders
-
In currently have in the workshop 16 sheets remaining, this should last us until mid-May
- Ti status:
- All CEH design files for baseplates have been updated
- For the 14 Ti sheets, 10 will be sent to industry for heat treatment, will be cutting some CEH-Partials with the remaining plates
- 500 CEH-Full plates to be order through industry to help bridge the gap of when Madras is able to deliver bulk amounts of Ti plates. This still has a lead time of ~8weeks
- Kapton status:
- All CEH design files for Kapton has been updated
- Need to check with Bernd the status of the 650 CEH-Full Kapton that has been
- Will have a follow-up discussion Tuesday (Mar 18th) of what needs to ordered through KIT to cover us until the CERN order goes through
Update from Jay:
- Will be designing new alignment jig for the Keyence machine (speeding up measurement time)
- Discussion with Tobias about vacuum pickup tool to avoid scratching the Glass (we are currently going though the protective sheets at ~1 sheet/week)
- All Keyence measurement programs has been updated and should now be faster.
- All shipped products will be uploaded to the central database on Monday (NTU was requesting this information)
Update from Yi-Mu:
- Production is going smoothly at ~10 plates/day
- Discussion of technicians is going OK, will need to talk about expectations of product.
- HiWi training is going well, most knows how to course correct if something goes wrong.
- Scheduling HiWi/technician next week if possible to see if there are unforeseen impedance mismatches with different personnel matching.
- Ramp up requirement:
- Curing shelf. Items has been sent to the workshop. Still needs machining and assembly.
- Scheduling of personnel needs to happen earlier with Stefan.
Outcome of workshop discussion:
- They won't cut more CuW
- Will send off the Ti plates for annealing
- Will cut some partials from the Ti if possible
- Will cut some dummies out of Al
- Will order 500 Ti Full plates from industry
- Need more materials to finish shelf for clean room.
- Main missing material are for the slide out shelves and weights.
- We only need 24 shelves for the initial ramp up test. We have asked if this partial request can be completed sooner with existing material
- Lead time of material purchase will be ~2weeks.